NEW QUESTION # 22
Which settings can you make in a production scheduling profile?
Note: There are 3 correct answers to this question.

  • A. Automatic goods issue on confirmation
  • B. Automatic print on order creation
  • C. Automatic goods receipt on confirmation
  • D. Default order types
  • E. Automatic release on order creation

Answer: C,D,E


NEW QUESTION # 23
What are some benefits of planning with planned independent requirements for finished materials?
Note: There are 2 correct answers to this question.

  • A. You have the option to use make-to-order production.
  • B. The delivery time is reduced.
  • C. You have the option to use forecast planning.
  • D. Manufacturing time for final assembly is reduced.

Answer: A,C


NEW QUESTION # 24
Which time elements are relevant for lead time scheduling of a production order?
Note: There are 2 correct answers to this question.

  • A. Opening period
  • B. Total replenishment lead time
  • C. Setup time
  • D. Float after production

Answer: C,D


NEW QUESTION # 25
Which of the following are features of the clean core dashboard?
Note: There are 2 correct answers to this question.

  • A. It can be used in all SAP S/4HANA Cloud editions.
  • B. Customers can use the dashboard in the dev, test, and production tenants.
  • C. Customers can grant access to the dashboard to partners.
  • D. It can be accessed by using SAP For Me.

Answer: C,D


NEW QUESTION # 26
Which of the following are replenishment strategies for Kanban containers?
Note: There are 2 correct answers to this question.

  • A. Replenishment using direct transfer posting
  • B. Replenishment using process orders
  • C. Replenishment using reservations
  • D. Replenishment using planned independent requirements

Answer: A,C


NEW QUESTION # 27
What are some SAP recommended guiding principles to achieve clean core operations?
Note: There are 3 correct answers to this question.

  • A. Establish release management.
  • B. Define roles and responsibilities as part of a process transformation office.
  • C. Integrate clean core practices in the end-to-end value process chain.
  • D. Establish an organizational structure, technical foundation, and transformation methodology for clean core.
  • E. Establish regular housekeeping tasks and procedures.

Answer: A,B,D


NEW QUESTION # 28
You want to verify that the properties of a component batch align with the required properties of the raw material intended for a specific process order. What function do you use to accomplish this?

  • A. Batch number assignment
  • B. Batch information cockpit
  • C. Batch where-used list
  • D. Batch determination

Answer: D


NEW QUESTION # 29
How are dependent requirements for assemblies created?
Note: There are 2 correct answers to this question.

  • A. They are created with exact times in Advanced Planning.
  • B. They are created together with the independent requirement for the finished product.
  • C. They are only created for multilevel bill of material (BOM) structures.
  • D. They are created on the assembly level during the planning run.

Answer: A,D


NEW QUESTION # 30
You want to set up a make-to-order planning scenario for a finished product. The bill of material contains two components: one should be procured for each sales order individually, and the other should be procured jointly for all independent requirements. Forecasting for the finished product is NOT possible. Which settings do you make to achieve this?

  • A. Choose planning strategy 20 (Make-to-Order) and select the corresponding Mixed MRP indicator
  • B. Choose planning strategy 20 (Make-to-Order) and select the corresponding Individual/Collective indicator
  • C. Choose planning strategy 50 (Planning without final assembly) and select the corresponding Individual/Collective indicator
  • D. Choose planning strategy 50 (Planning without final assembly) and select the corresponding Mixed MRP indicator

Answer: B


NEW QUESTION # 31
How can you achieve a feasible production plan when there are capacity constraints?
Note: There are 3 correct answers to this question.

  • A. Increase the capacity supply in a time-phased interval
  • B. Execute an infinite production planning run for the critical resources
  • C. Determine a time period with available capacity on the planning board
  • D. Form optimum sequences to reduce setup times
  • E. Reduce the planning time interval

Answer: A,C,D


NEW QUESTION # 32
Which of the following would you recommend as SAP's strategic Sales and Operations planning tool?

  • A. Standard Sales and Operations Planning
  • B. Advanced Planning
  • C. Flexible Planning
  • D. Integrated Business Planning

Answer: D


NEW QUESTION # 33
You use the Finite Scheduling - with Reverse planning strategy and want to allow scheduling in the past.
How can you parameterize this in the strategy profile?

  • A. Specify a negative offset time
  • B. Specify a negative opening period
  • C. Specify a negative PP/DS horizon
  • D. Specify a negative planning horizon

Answer: A


NEW QUESTION # 34
Under what circumstances can you change the material type for a material if stocks, reservations, or purchasing documents exist? Note: There are 2 correct answers to this question.

  • A. The same account category is used.
  • B. The same base unit of measure is used.
  • C. The quantity and value updates are the same.
  • D. The same batch management level is used.

Answer: B,C


NEW QUESTION # 35
What are some options for creating a production order?
Note: There are 2 correct answers to this question.

  • A. By setting a Kanban container to empty
  • B. By setting a Kanban container to full
  • C. By converting a purchase requisition
  • D. By partially converting a planned order

Answer: A,D


NEW QUESTION # 36
Which time elements does MRP consider in backward scheduling to determine the basic dates for components from dependent requirements? Note: There are 2 correct answers to this question.

  • A. Planned delivery time
  • B. Total replenishment lead time
  • C. In-house production time
  • D. Operation duration

Answer: A,C


NEW QUESTION # 37
Which of the following is a scheduling method for a production order?

  • A. Determination of delivery date
  • B. Lead time scheduling
  • C. Key date scheduling
  • D. Determination of basic dates

Answer: B


NEW QUESTION # 38
......