SAP C_TS412_2021 exam is a valuable certification for individuals who want to demonstrate their skills in SAP S/4HANA Project Systems. It covers a wide range of topics, from project planning to project progress, and provides a solid foundation for individuals who want to advance their careers in project management and SAP consulting. Passing the exam requires a thorough understanding of the topics covered, as well as practical experience in implementing and configuring SAP S/4HANA Project Systems.
SAP C_TS412_2021 certification is recognized globally and is highly valued by employers. It provides professionals with a competitive edge in the job market and can lead to higher salaries and career advancement opportunities. Professionals who have achieved this certification are considered experts in SAP S/4HANA Project Systems and are in high demand across various industries.
NEW QUESTION # 45
Which of the following factors influence the scheduling of internal processing activities? Note: There are 3 correct answers to this question
- A. The relationships between activity elements
- B. Whether the work for the internal activity is greater than its duration
- C. The factory calendar in the work center used for the internal processing activity
- D. The unit (for example, hour, day) of the field Normal Duration field of the activity
- E. An activated Scheduling indicator in the control key of the internal processing activity
Answer: A,C,E
Explanation:
The scheduling of internal processing activities is influenced by several factors, such as the control key, the activity elements, and the factory calendar. The control key is a parameter that defines the basic properties of an activity, such as whether it is internally or externally processed, whether it requires confirmation or not, and whether it is relevant for scheduling or not. The scheduling indicator in the control key determines whether an activity is included in scheduling or not. The activity elements are subordinate units of an activity that represent partial tasks or work packages. The relationships between activity elements define the logical sequence and dependencies of the partial tasks. The factory calendar is a parameter that defines the working days and holidays for a work center. The factory calendar affects the duration and dates of an activity that uses the work center. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
NEW QUESTION # 46
Which statement is valid regarding networks?
- A. Material components can be assigned to activity elements
- B. Relationships can be used to connect activities of different networks
- C. A network can be activity-account-assigned and header-account-assigned
- D. A network activity can be assigned to several WBS elements
Answer: B
Explanation:
One statement that is valid regarding networks is that relationships can be used to connect activities of different networks. Networks are structural elements of a project that represent processes or operations within a project. Networks consist of various activities that represent tasks or partial tasks within a network. Relationships are logical connections between activities or networks that define the sequence or dependency of their execution. Relationships can be used to connect activities of different networks in order to model complex processes that span across multiple networks. For example, you can use a finish-start relationship to indicate that an activity in one network cannot start until an activity in another network is finished. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
NEW QUESTION # 47
You want to allocate overhead rates to a WBS element. What must you assign to the WBS element?
- A. Settlement rule
- B. Costing sheet
- C. Results analysis key
- D. Investment profile
Answer: B
Explanation:
To allocate overhead rates to a WBS element, you must assign a costing sheet to the WBS element. A costing sheet is a tool that allows you to define and calculate overhead costs based on various criteria, such as plant, company code, material origin, or order type. You can assign a costing sheet to a WBS element in the Control Data tab of the WBS element master data. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/df72bb53707db44ce10000000a174cb4.html
NEW QUESTION # 48
Which of the following actions can transfer actual costs for external processing? Note: There are 2 correct Answers to this question.
- A. Saving a supplier invoice
- B. Saving a purchase order
- C. Saving a goods receipt
- D. Saving a service entry sheet
Answer: C,D
NEW QUESTION # 49
You want to determine the planned costs for an internally processed activity. Which data do you need?
Note: There are 2 correct Answers to this question.
- A. Work
- B. Activity type
- C. Profit center
- D. Duration
Answer: A,B
NEW QUESTION # 50
What functions are available for period end closing in SAP Project System? Note: There are 3 correct answers to this question
- A. Progress analysis
- B. Settlement
- C. Results analysis
- D. Milestone trend analysis
- E. Confirmations
Answer: A,B,C
Explanation:
Settlement, progress analysis, and results analysis are some of the functions available for period end closing in SAP Project System. Settlement is used to allocate the costs and revenues in projects or the results analysis data to one or more receivers, such as cost centers, profitability segments, or assets. Progress analysis is used to determine and compare the planned and actual project progress values, based on the overall planned costs and the work done. Results analysis is used to perform a periodic valuation of the project, based on the costs and revenues expected or incurred in the project. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
NEW QUESTION # 51
What is the reason for assigning billing plans in customer projects?
- A. Billing plans are used for revenue planning
- B. Billing plans are copied automatically to the sales order item.
- C. Billing plans enable the billing process to be carried out
- D. Billing plans are prerequisites for quotation creation
Answer: A
Explanation:
Billing plans are used for revenue planning in customer projects because they allow you to define billing dates and billing amounts for each project phase or milestone. Billing plans can also be used to create billing requests or invoices automatically based on the billing dates and amounts. Billing plans help you to plan and monitor the cash flow and profitability of your customer projects. Reference: https://help.sap.com/viewer/0c9a2f8f9c1b4a2e8b3f7d0c9b6e1d8a/2020.000/en-US/4c5f7a3e6b571014e10000000a174cb4.html
NEW QUESTION # 52
Which statement is valid regarding networks? Note: There are 2 correct Answers to this question.
- A. A network activity can be assigned to several WBS elements.
- B. Material components can be assigned to activity elements.
- C. Relationships can be used to connect activities of different networks.
- D. A network can be activity-account-assigned and header-account-assigned.
Answer: C,D
NEW QUESTION # 53
You use networks and internal activities in your project. You have activated capacity requirements and notice that one work center is overloaded. You have no authorization to change the work center. How can you reduce the overload of the work center? Note: There are 2 correct answers to this question
- A. Increase the capacities of the work center in the project planning board.
- B. Shift activities backward or forward on the time axis where more capacities are available
- C. Trigger automatic capacity leveling inside the project planning board
- D. Maintain subordinate internal activity elements assigned to other work centres
Answer: B,C
Explanation:
Capacity requirements are the demand for capacities that result from planned or actual orders. If a work center is overloaded, it means that its capacity requirements exceed its available capacities. To reduce the overload of the work center, you can trigger automatic capacity leveling inside the project planning board, which is a tool that allows you to plan and monitor capacities for network activities. You can also shift activities backward or forward on the time axis where more capacities are available, which means changing their start and finish dates manually or automatically. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
NEW QUESTION # 54
Resources
Which of the following transactions can you use to post actual cost for external processing.
Note : there are 2 correct answer for this question.
- A. Approval of a good receipt.
- B. Creating a purchase order.
- C. Creating a service entry sheet
- D. Posting a goods receipt
- E. Approval of a service entry sheet
Answer: A,E
Explanation:
The approval of a service entry sheet and the approval of a goods receipt are both transactions that can be used to post actual costs for external processing." Reference: 3
NEW QUESTION # 55
Which objects can be used to specify settlement rules? Note: There are 2 correct Answers to this question.
- A. Network header for activity-account-assigned networks
- B. Standard WBS elements
- C. Network activity for activity-account-assigned networks
- D. WBS elements
Answer: A,D
NEW QUESTION # 56
Which sales documents can update planned revenues on WBS elements? Note: There are 2 correct answers to this question
- A. Quotation
- B. Inquiry
- C. Sales order
- D. Billing
Answer: C,D
Explanation:
Sales order and billing are some of the sales documents that can update planned revenues on WBS elements. Sales order is a document that records a customer's request for goods or services from a sales organization. Billing is a document that records the delivery of goods or services to a customer and requests payment for them. Both sales order and billing can update planned revenues on WBS elements if they are assigned to them directly or indirectly via network activities. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
NEW QUESTION # 57
You plan an activity that starts on February 1 and finishes on February 28. For this activity, you want to define a milestone for February 10 which should NOT be changed through scheduling. What do you recommend for milestone definition?
- A. Enter 10 days as duration
- B. Enter an offset of 10 days to the start date of the activity
- C. Enter February 10 as fixed date
- D. Enter an offset of -18 days to the finish date of the activity
Answer: C
Explanation:
To define a milestone for February 10 that should not be changed through scheduling, you should enter February 10 as fixed date for the milestone. A fixed date is a date that remains unchanged during scheduling, regardless of any changes in the dates of preceding or succeeding activities or milestones. A fixed date can be entered manually or automatically derived from a constraint. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
NEW QUESTION # 58
Revenues & Payment
A customer use cross- company - code project with a top billing element and additional billing element underneath (por debajo) for each company code. Although the internal .. correctly the result analysis summarizes all values to the highest billing element. How can they split the results to the different company codes?
- A. Settle the WBS element to the highest billing element before you do the result analysis.
- B. Split the project intdifferent project according to each company code.
- C. Adjust the customizing of the valuation method in the expert mode of the periodic results analysis accordingly.
- D. Change the project structure so that it correspond better to the company's organization structure.
Answer: D
NEW QUESTION # 59
You have created an internally-processed network activity, and assigned a work center and the work. After saving, you discover that no planned costs are displayed in the cost element report for the activity. What could be the reason? Note: There are 3 correct answers to this question
- A. Integrated planning for the network is active
- B. The activity output price for the activity type and cost center assigned to the work center is not maintained.
- C. The formula for costing in the work center is incorrect
- D. The Determine Costs indicator in the network header rules out planned cost calculation
- E. The duration is missing in the activity
Answer: B,C,D
Explanation:
Planned costs are calculated for internally-processed network activities based on the formula for costing in the work center, the activity output price for the activity type and cost center assigned to the work center, and the duration of the activity. If any of these factors are missing or incorrect, no planned costs will be displayed. The Determine Costs indicator in the network header also controls whether planned costs are calculated or not. If it is not set, no planned costs will be displayed. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
NEW QUESTION # 60
What PPIDS master data is necessary for using PP/DS? Note: There are 2 correct answers to this question
- A. Material
- B. Production version
- C. Location
- D. Resource
Answer: A,D
Explanation:
PPIDS master data is necessary for using PP/DS, which is a component of SAP APO that provides advanced planning and scheduling functions for production planning and detailed scheduling. PPIDS master data includes material and resource data. Material is a set of data that defines the characteristics and properties of a product that can be produced or procured. Resource is a set of data that defines the characteristics and capacities of a production facility that can be used to produce products. Reference: https://help.sap.com/doc/saphelp_scm700_ehp02/7.0.2/en-US/69/f3055130534338e10000000a154ce5/content.htm
NEW QUESTION # 61
You use a WBS project structure with network and maintenance order. You want to schedule both the network and the maintenance order .
What do you have to consider?
- A. The maintenance orders must be assigned to the same plant as the network.
- B. The maintenance orders must be assigned as sub-networks.
- C. The maintenance orders must be assigned to WBS element.
- D. The maintenance order s must be assigned to the same budget profile as the project definition.
Answer: A
NEW QUESTION # 62
You used reductions to reduce the scheduled duration of all internally-processed activities in your project. However, the duration did not changed after overall network scheduling. What do you check? Note: There are 2 correct answers to this question
- A. If the maximum reduction level is less than 100
- B. If the reduction strategy is set in the network header
- C. If the reduction strategy is set in each activity
- D. If the appropriate reduction type is set in the parameters for network scheduling
Answer: A,D
NEW QUESTION # 63
You want to make sure that certain tasks must start on a given date. Where can you maintain constraints for start dates?
- A. Activity
- B. Milestone
- C. Network header
- D. Activity element
Answer: A
Explanation:
To maintain constraints for start dates, you can use activities. Activities are structural elements of a network that represent tasks or partial tasks within a project. Constraints are parameters that define fixed dates or time intervals for activities or networks. Constraints can be used to influence the scheduling of project objects and to ensure that certain deadlines are met. You can maintain constraints for start dates or finish dates of activities or networks in the project builder or the project planning board. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
NEW QUESTION # 64
Which of the following business processes do NOT lead to the booking of actual costs to an object?
Note: There are 2 correct Answers to this question.
- A. Goods receipt of a non-stock item
- B. Goods receipt into unvaluated project stock
- C. Goods receipt into valuated project stock
- D. Recording of external services in the service entry sheet
Answer: B,D
NEW QUESTION # 65
......